premier marine contracting

Marine Contracting

Stefanutti Stocks’ marine infrastructure construction experience spans almost three decades during which it has successfully completed many complex and challenging marine infrastructure projects throughout the African continent.

Our solution-focused offering, that includes the design and build contracting model, has made us an invaluable construction partner – to port operators, mining industry clients, as well as to the bulk handling, oil & gas and energy sectors. We also offer construction only project delivery model.

Our high-calibre, highly-skilled construction teams have vast experience in the marine construction field; we foster strong stakeholder relationships, both locally and internationally; we focus on the development of innovative alternative construction methodologies; we are solutions focused to provide cost and time savings; our health, safety and quality is world-class and we have a sterling safety record.

excellence in execution

Our marine contracting capabilities include:

  • Comprehensive shoreline and port development experience.
  • Full project lifecycle involvement, from pre-feasibility through to construction and commissioning stages.
  • Construction of land and ocean-side marine infrastructure.
  • Construction of associated civil infrastructure (industrial, petrochemical, transport).

Our marine contracting services include the construction of:

  • jetties and berths
  • piled quay walls (our marine piling capabilities include sheet piling and combi wall pile driving)
  • deck on piles
  • breakwaters and revetments
  • scour protection and dredging
  • caissons and pre-cast structures
  • slipways and boat ramps
  • concrete repair and rehabilitation
  • back of quay civils works
  • desalination plants, cooling water intake & outfall pipelines & associated structures
  • shore crossing

Projects

The Western Cape Region recently completed a six-month project for Transnet that entailed the procurement of new V-fenders, and replacement of the existing fenders at Port Ngqura’s container terminal berths. This was Phase 2 of Transnet’s fender replacement programme, with Phase 1 having been executed by the Coastal region.

A 12-month long marine project for Transnet, located in East London, comprises the deepening and widening of N-berth. In order to extend the quay wall by 1,5m to align with the adjacent quay Stefanutti Stocks is casting new concrete fender blocks and cantilever slabs on the quay face, followed by fitting new tyre fenders. The project, while small, has a very technical scope that entails casting the fender blocks – that have their undersides below low tide water level – “in the dry” by using specially designed purpose-built watertight shutters. This project will continue until November 2024.

Some of our further landmark marine projects include:

  • Upgrade to berths 1 to 4, 13 and 14 of Maydon Wharf for Transnet, KZN, South Africa 2014-2018
  • Marine works for Strandfontein desalination plant for PROXA, Western Cape, South Africa 2018
  • Quarry and Port Civil Works for the Bel Air Mine, Guinea 2017-2018
  • Port Nolloth marine infrastructure rehabilitated for Transnet, Northern Cape, 2016-2017
  • New Kissy Oil Jetty for Oryx Energies, Peninsula Freetown, Sierra Leone 2013-2015
  • Kwale Mineral Sands projects for Base Titanium Limited, Kenya 2013
  • Construction of new liquid chemical berth (Berth 208) for Transnet, KZN 2010
Scour protection to Berth A and Berth B, for Transnet, 2023

Scour protection to Berth A and Berth B, for Transnet, 2023

During May and December 2023 Stefanutti Stocks’ Coastal Region undertook the scour protection to Berth A and Berth B, for Transnet, as the quay wall that berths cruise liners, had over time been undermined and scoured.
The project included dredging and placing the seabed to the design level. A double layer of A10 Geotextile was placed, followed by a 1 000mm layer of armour rock, that forms a barrier to stop future scouring from prop wash and side thrusters. The voids (250m3) below the quay wall were filled with concrete, and this was completed 11 meters beneath the water.

The works were completed using a 36m x 19m barge with an 80ton Long Reach Excavator (LRE) secured to it. To enable the underwater works to be completed the LRE was fitted with a dig system GPS, which together with post multi-beam surveys was the only way to “view” the works.

The armour rock was loaded into a 6m3 skip before being lowered into the water by a 135ton Crawler Crane.

During the contract Stefanutti Stocks teams worked two twelve hour shifts, Monday to Friday, as well as a shift on Saturday.

The project was successfully completed, in time for the MSC Splendida to be berthed on 22 November 2023, ready for the start of the Cruise Season.

Quarry and Port Civil Works for the Bel Air Mine, Guinea 2017-2018

Quarry and Port Civil Works for the Bel Air Mine, Guinea 2017-2018

This mining infrastructure development project, undertaken by Stefanutti Stocks Coastal in French-speaking Guinea, entails the construction of a 1 400m long rock breakwater, with a 100-metre-long precast concrete barge berth. The project scope includes the greenfield establishment and operation of an armour rock quarry – to drill and blast over 500 000m3 of rock fill. Furthermore, a precast yard was established on site to manufacture the berth wall components and provide in situ concrete for the cope beam.

In April 2018 the project reached the milestone of 750 000 Lost Time Injury Free man hours worked.

Stefanutti Stocks Coastal_Kwale_ship loader installation 1

Kwale Mineral Sands projects for Base Titanium Limited, Kenya 2013

The Kwale Mineral Sands project was awarded based on an alternate design that allowed for a reduced contract price through a reduction of both the concrete volume and the pile steel quantities.

Stefanutti Stocks Coastal proposed an alternative solution that entailed the use of prefabricated structural steel headstocks (nine in total) in lieu of reinforced concrete platforms. The headstocks were also utilised as pile guides, whereby the installation of the raker piles and structural steel headstocks were concluded simultaneously. This methodology translated into savings on cost and time.

The marine infrastructure work consisted of a conveyor (access) trestle, a concrete decked load-out platform with crane rails for a ship loader, two mooring dolphins and two berthing dolphins. Structural steel elements were manufactured in South Africa and then shipped to Mombasa. The marine piling comprised of 60 steel tube piles including compression; tension piles up to 45 metres in length; upright piles; as well as 1:4 raker piles.

While Stefanutti Stocks was busy with the Kwale Mineral Sands Marine infrastructure project, client Base Titanium Ltd also appointed the marine contractor to assemble its ship loader. The project included pre-assembly; dummy erection in Durban; loading for transportation; offloading in Mombasa and the final erection of the Kwale Mineral Sands Ship loader in Mombasa Kenya. The erection was undertaken from three barges on three work-fronts. The lifts consisted of various loads with the largest lift being a 90-ton tandem lift off from a floating barge. Once all the barges and cranes were off-hired, the final fitment of the smaller mechanical items and the electrical and instrumentation installation started. The on-site installation process took four months to complete before cold commissioning could begin in early November 2013.

Stefanutti Stocks Coastal_Marine_Maydon Wharf completed construction Berth 3 and 4

Upgrade to berths 1 to 4, 13 and 14 of Maydon Wharf for Transnet, KZN, South Africa 2014-2018

A joint venture, consisting of Stefanutti Stocks Coastal and its enterprise development partner, Axsys Projects, used some technical innovations while reconstructing and deepening the six berths that form the Port of Durban’s largest break-bulk, edible-oils and dry bulk-handling precinct.

The scope of work, included a new HZM-AZ combination wall system with anchor piles, a new cope, underwater sheet pile installation, earthworks, re-surfacing, dredging and scour protection.

Techniques, never used in South Africa, were implemented for the installation of anchor piles, as well as the in-situ construction of the submerged fender panels for the cope structure.

This marine construction project was named the winner of the Railway & Harbour category in the 2016 SAICE-SAFCEC Awards.
In March 2017 the project achieved 2-million Lost Time Injury Free man hours worked.

PORT NOLLOTH MARINE INFRASTRUCTURE REHABILITATED FOR TRANSNET, NORTHERN CAPE, 2016-2017

Port Nolloth marine infrastructure rehabilitated for Transnet, Northern Cape, 2016-2017

The scope of marine infrastructure refurbishment undertaken by Stefanutti Stocks Coastal at Port Nolloth, included:

  • removal of existing tyre fenders;
  • installation of new tyre fenders;
  • refurbishment of existing bollards;
  • concrete rehabilitation to the side faces and underside of the jetty structure; and
  • rock revetment construction.

The water-based remedial work, undertaken to the underside of the jetty structure was accessed using a temporary access platform constructed below neap low tide level.

The 70-metre rock revetment was completed within five months, by offloading and placing rocks using special excavator mounted thumbs welded onto an excavator boom on site.

Stefanutti Stocks Coastal_Marine_Berth 208

Construction of new liquid chemical berth (Berth 208) for Transnet, KZN 2010

Stefanutti Stocks Coastal constructed the new Liquid Chemical Berth 208 for Transnet Capital Projects (TCP). This marine infrastructure construction project included the positioning of 72 reinforced precast concrete beams, which had to straddle adjacent pile caps. The beams, weighing between 65 and 75 ton were placed off a barge and this activity required careful planning in order to optimise safe working conditions. The beams could not be placed if the wind speed exceeded 40km/hr, if wave heights exceeded 0.5m and/or if tidal heights weren’t within a specific window.
Desalination_IMG_1990

Marine works for Strandfontein desalination plant for PROXA, Western Cape, South Africa 2018

Stefanutti Stocks Coastal, in joint venture with TAG Diving undertook the marine scope of work for the Strandfontein desalination plant. The bulk of the original scope of work was completed within a period of nine weeks and included the procurement, manufacture, installation and commissioning of the plant and materials for the Strandfontein seawater intake line, brine line and pump station.

Through early contractor involvement Stefanutti Stocks Coastal and PROXA’s design engineer, PRDW, value engineered the pipe-line configuration to achieve an excellent balance between the design requirements (for the total weight and stability of the pipeline on the seabed), and the practicality of manufacturing and installing this pipeline. The outcome was a dual pipe – two 600-metre long, 500mm OD HDPE piping – installed side by side in the pipe-stringing yard.

The pipe was launched in two 300-metre long strings, with the first string including the 144-metre brine line. The launching and towing was undertaken by a tug boat (with a 500-metre towline attached to the pipeline) and six synchronised excavators walking the pipeline into the sea.

Stefanutti Stocks Coastal_Marine_Berth 208

New Kissy Oil Jetty for Oryx Energies, Peninsula Freetown, Sierra Leone 2013-2015

This project entailed the design and construction of a new fuel import facility to support the safe importation of fuels into Sierra Leone. The new jetty replaced the existing facility, which was beyond its operational lifespan and did not conform to international standards. Stefanutti Stocks and its joint venture partner were awarded the project on an EPC FIDIC Silver Book Contract basis, in 2013.

The turnkey scope of works began with design, followed by construction work consisting of:

  • a steel piled substructure with mooring and berthing dolphins,
  • a prefabricated superstructure for both liquid product lines,
  • a firefighting system, and
  • the final testing and commissioning of the system.

The design was optimised by using prefabricated steel structures manufactured in the Netherlands. This resulted in no delay due to the lack of local supplies and ensured a rapid construction programme. The project, that commenced in early 2014 was delayed for eight months due to the Ebola epidemic. Once the epidemic receded the staff were remobilised and the project was successfully completed in 2015.

Contact:

Coastal Region: +27 31 835 3300
Address: 59 Henwood Road, New Germany, Pinetown, 3610

Western Cape Region: +27 21 834 6700
Address: Manhattan Close, Airport Industria, Cape Town, 7525